Workflow
- Compare the signed baseline to executed COs before using the pending totals.
- For a pending revision of an approved item, compare the new proposal to that item’s existing approved value.
- Review the pending proposal total alongside net incremental exposure when preparing the forecast.
Worked example
An approved $5,000 CO with a pending $6,200 revision leaves signed value unchanged. Its pending proposal is $6,200 and incremental exposure is $1,200.