Approved versus pending change order exposure tracker

Separate newly proposed and revised change exposure from commitments already included in the current signed construction contract amount.

Workflow

  1. Compare the signed baseline to executed COs before using the pending totals.
  2. For a pending revision of an approved item, compare the new proposal to that item’s existing approved value.
  3. Review the pending proposal total alongside net incremental exposure when preparing the forecast.

Worked example

An approved $5,000 CO with a pending $6,200 revision leaves signed value unchanged. Its pending proposal is $6,200 and incremental exposure is $1,200.

Open the change order workbench

Questions and answers

Can pending exposure be negative?

Yes. A pending credit or a revision below its approved value creates a negative incremental adjustment.