How to show bond and insurance fees on change orders

Show a contract-approved bond or insurance adjustment on its own line so reviewers can compare it with the cost base and OH&P.

Workflow

  1. Check whether the contract applies a separate fee and how it defines the basis.
  2. Calculate the permitted fee with the required contract method and enter that dollar amount separately.
  3. Keep the supporting calculation with the sign-off and check the combined change amount.

Worked example

A $1,500 base plus $150 OH&P and an approved $24.50 fee produces a $1,674.50 change.

Open the change order workbench

Questions and answers

Is the separate fee included in the OH&P basis?

The workbench adds the supplied fee after OH&P, keeping the fee visible for review.