Workflow
- Start with the executed base amount and confirm any amendments included in that figure.
- Select the latest approved revision for every change and sum additions and credits using consistent signs.
- Cross-check the revised sum with the latest executed contract value and investigate any variance.
Worked example
An $820,000 original sum, $27,400 of approved additions and $8,250 in signed credits produce a revised signed value of $839,150.