How to reconcile the revised construction contract sum

Reconcile the original contract sum with signed additions and deductive changes, and keep open proposals in a separate line for the owner.

Workflow

  1. Start with the executed base amount and confirm any amendments included in that figure.
  2. Select the latest approved revision for every change and sum additions and credits using consistent signs.
  3. Cross-check the revised sum with the latest executed contract value and investigate any variance.

Worked example

An $820,000 original sum, $27,400 of approved additions and $8,250 in signed credits produce a revised signed value of $839,150.

Open the change order workbench

Questions and answers

Should I add allowances already in the base sum again?

Record the approved adjustment against the original allowance. Leave the existing allowance in the base amount.