Workflow
- Record the unit used in the contract and convert or enter the agreed change in calendar days.
- Keep the dated schedule narrative and identify any overlapping impacts for the reviewer.
- Update a signed time adjustment after execution and reconcile the resulting milestone in the project schedule.
Worked example
A signed two-day adjustment plus a pending revision requesting five days shows three incremental pending days. Overlapping impacts still need schedule review.