Construction change order log template and PDF generator

Build a contractor change register with original contract sum, PCO and COR history, approved changes, pending exposure and owner approval PDFs.

Workflow

  1. Enter the signed base contract amount. Use a consistent Change ID from first estimate through execution.
  2. Log each proposal or revision separately with its type, revision number, cost basis, fee and calendar days.
  3. Reconcile the selected approved revisions to executed records before circulating the owner log.

Worked example

A $450,000 original contract plus one $1,650 approved revision has a $451,650 revised signed value. A separate $875 request stays in pending exposure.

Open the change order workbench

Questions and answers

Can I bring in an existing register?

Yes. Map your columns to the workbench CSV header and import up to 150 rows including revisions.