Workflow
- Enter the signed base contract amount. Use a consistent Change ID from first estimate through execution.
- Log each proposal or revision separately with its type, revision number, cost basis, fee and calendar days.
- Reconcile the selected approved revisions to executed records before circulating the owner log.
Worked example
A $450,000 original contract plus one $1,650 approved revision has a $451,650 revised signed value. A separate $875 request stays in pending exposure.