How to clear a construction change order reviewer queue

Prioritize pending approvals, duplicate revisions and OH&P cap exceptions before releasing a project log to an owner or architect.

Workflow

  1. Review duplicate active rows first so each Change ID and revision has an unambiguous status.
  2. Compare over-cap categories to the source contract clause and record the pricing resolution.
  3. Assign the remaining pending decisions and record a reviewer and decision date in the workbook.

Worked example

Two Approved copies of CO-031 Rev 2 hold that revision for review. After the duplicate is resolved, the approved amount can enter the signed total.

Open the change order workbench

Questions and answers

Does an over-cap flag change the submitted amount?

The flag makes the entered rate visible for review. The report preserves the entered figures.