Construction change order sign-off checklist for owners and GCs

Assemble a consistent owner approval packet with scope, cost categories, OH&P basis, contract value and a documented schedule decision.

Workflow

  1. Reference the specific revision and source documents such as an RFI, drawing bulletin or subcontractor quote.
  2. Compare line items and markup against the contract and preserve adjustment notes with the audit sheet.
  3. Record the authorized signatures, date and final price and time change in the official project records.

Worked example

The architect confirms scope for SK-21, the contractor validates labor and equipment, and the owner authorizes a $3,180 increase plus one calendar day.

Open the change order workbench

Questions and answers

Do generated signature fields complete execution?

The pack provides blank review fields. Follow the authorization and execution process established by the contract.