How to record a construction deductive change order

Document scope removed from a construction contract, preserve the deductive credit and trace its effect on the signed and pending totals.

Workflow

  1. Identify the omitted scope and preserve the supporting original estimate or schedule of values.
  2. Enter the credit as a positive magnitude in the deductive credit field.
  3. Confirm the net amount with the reviewer before marking a deductive revision Approved.

Worked example

A signed $7,250 credit and a $638 accepted add in the same revision produce a $6,612 reduction when there are no additional fees.

Open the change order workbench

Questions and answers

Can the log contain both added work and a credit on one revision?

Yes. Itemize the added cost base and enter the deductive credit separately.