Custom home allowance credits and upgrade change orders

Track allowance credits and owner-selected upgrades so the total contract increase can be matched to the final approved selections.

Workflow

  1. Identify the original allowance, what it covered and whether labor was included.
  2. Record the approved allowance credit separately from the accepted product and installation costs.
  3. Retain unapproved selections in the pending queue and replace superseded quotes with a later revision.

Worked example

A $12,500 appliance allowance credit and a $17,325 approved upgrade yield a $4,825 signed contract increase.

Open the change order workbench

Questions and answers

What happens when a homeowner changes the selection again?

Keep the earlier quote in the log and issue a new revision for the final choice.