PCO and COR revision tracking spreadsheet for contractors

Trace a potential change from Rev 0 through the change order request and signed CO while preserving each earlier version in the register.

Workflow

  1. Keep the stable Change ID across pricing stages and revisions. Put PCO, COR or CO in the type column.
  2. Increment the revision when scope, price or time changes and mark the withdrawn proposal Superseded.
  3. Mark the executed version Approved and compare Revision History with the active Change Register.

Worked example

CHG-018 Rev 0 is superseded at $2,400. Rev 1 is signed for $2,850. Rev 2 proposes $3,100, so net incremental exposure is $250.

Open the change order workbench

Questions and answers

Does a COR create a second signed amount?

Use the same Change ID when the COR is a new stage of the same scope. Only the latest approved revision contributes to the signed register.