Subcontractor overhead and profit markup calculator for change orders

Calculate overhead and profit in basis points, compare entered rates with trade and self-performed work caps, and show the bond fee separately.

Workflow

  1. Split labor, material, equipment and subcontract values into the corresponding cost bases.
  2. Enter the requested OH&P rate and set the maximum rate for each category to the contract limits.
  3. Compare the audit sheet with the pricing clause and correct over-cap rows before execution.

Worked example

$1,000 labor plus $500 materials at 1,000 bps gives $150 OH&P and $1,650 before separate fees or credits.

Open the change order workbench

Questions and answers

What if a row needs different rates by category?

Calculate the distinct scopes separately. Each register row uses one entered rate and checks it against every populated category cap.